NAB has foresee operational cost reductions of $22 million over 7 years as it consolidates 20 datacentres and mechanism rooms
By Hamish Barwick, Sydney | Monday, 11 Feb 2013
National Australia Bank (NAB) has foresee operational cost reductions of $22 million over 7 years as it consolidates 20 information centres and mechanism bedrooms down to dual comforts in Melbourne.
Speaking during a media lecture in Sydney, NAB CTO Denis McGee pronounced that a new information centre in Deer Park will be strictly denounced on 12 February. However, a trickery won’t be entirely operational until Q4 of 2013 as a bank continues a information centre converging program. It de-commissioned 3 bequest information centres in a final 12 months.
NAB sealed a long-term franchise with Digital Realty Trust in Q4 of 2011 to take space in a vendor’s Melbourne information centre. The bank also operates an existent information centre in Knox.
NAB moves to `infrastructure on demand’
IT mutation hurdles still forward for NAB: Slater
NAB outlines information centre converging strategy
“That [consolidation] will have a estimable impact on a use of energy. The 20 information centres devour about 40 per cent of a bank’s energy,” McGee said.
He combined that a Deer Park trickery will broach a CO rebate of 3200 tonnes and a energy saving of 9.1 million kilowatts per hour over a subsequent 10 years for a bank.
According to McGee, a energy utilization potency (PUE) will be reduction than 1.3 PUE during a new information centre.
“The module will eventually revoke NAB’s record use by 40 per cent when we connect all of those information centres.”
NAB is now 4 years into a NextGen IT mutation module that includes an renovate of a core banking system, applications, infrastructure and networks.
Follow Hamish Barwick on Twitter: @HamishBarwick
Follow Computerworld Australia on Twitter: @ComputerworldAU, or take partial in a Computerworld review on LinkedIn: Computerworld Australia
Article source: http://reseller.co.nz/reseller.nsf/inews/nab-to-save-22-million-with-datacentre-consolidation-program